RM34m Papar flood mitigation project
Published on: Sunday, August 21, 2022
By: Bernama
Text Size:

RM34m Papar flood mitigation project
Tuan Ibrahim (4th from left) and others during the site visit at Kg Pengalat Besar.
PAPAR: The Federal Government has allocated RM34 million to implement a flood mitigation project to deal with the flood problems in this district and surrounding areas, which will begin early next year.

Environment and Water Minister Datuk Seri Tuan Ibrahim Tuan Man said the scope of the project is to build a 1,150-metre long beach barrier structure and erosion protection structure in Kampung Kuala Dalam.

“Apart from that, the project also involves the construction of three units of water control gates and deepening of the area where boats anchor. This project is expected to be completed within three years.

“The flood mitigation project in Kampung Kuala Dalam will be carried out with site cleaning, dredging and land reclamation and construction of coastal erosion control structures as well as deepening the mouth of Sungai Papar,” he said after inspecting the project site, Saturday.

He said the erosion problem at the beach in Kampung Kuala Dalam has been happening for more than 10 years and became more serious in the last two years.

“This matter is causing problems for the residents who mostly work as fishermen...almost 250 houses with about 1,000 residents here are facing the risk of coastal erosion and flooding,” he added.

At the same time, Tuan Ibrahim said his Ministry, through the Department of Irrigation and Drainage (JPS), had also planned to implement several other projects to overcome the flood problems in the Membakut area. “These include the proposed construction of the Sungai Membakut river flood way to Sungai Binsuluk by dredging the rivers in the areas at risk of floods, as well as construction of bank stabilisation structures.

“We propose to implement the Sungai Padas Beaufort conservation project to overcome the problem of river bank erosion in Kampung Lubuk Hilir, Kampung Lupak and Kampung Suasa through the construction of bank stabilisation structures. “This project has been requested in the Third Rolling Plan of the 12th Malaysia Plan (RMK12),” he said.

He said his Ministry, through the JPS, is also carrying out the Membakut River Basin Flood Mitigation Master Plan Development Study, which involves four rivers, namely Sungai Membakut, Sungai Damit, Sungai Terusan River and Sungai Binsuluk.

“This study aims to identify the problem of flooding in the areas involved and plan short, medium and long-term solutions. “It is currently at the follow-up stage as of Aug 1 and is expected to be completed on Feb 1, 2023 at a cost of RM476,171,” he said. 

* Follow us on Instagram and join our Telegram and/or WhatsApp channel(s) for the latest news you don't want to miss.

* Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available.





ADVERTISEMENT






Top Stories Today

Sabah Top Stories


Follow Us  



Follow us on             

Daily Express TV  







close
Try 1 month for RM 18.00
Already a subscriber? Login here
open

Try 1 month for RM 18.00

Already a subscriber? Login here